Growth and Transformation Plan II (GTP II) 2016-2020
Growth and Transformation Plan II (GTP II) 2016-2020 was adopted in May 2016 and replaces GTP I covering years 2011-2015. GTP II is a comprehensive strategy to improve economic condition of Ethiopia and includes energy and renewable energy targets guiding country’s development.
Energy and renewable energy capacity targets:
| 2014/2015 levels (MW) | 2019/2020 targets (MW) |
Overall power capacity (fossil and non-fossil) | 4,180 | 17,208 |
of which |
|
|
Hydropower |
| 13,817 |
Wind |
| 1,224 |
Solar PV |
| 300 |
Geothermal |
| 557 |
reserve fuel (gas turbine) |
| 509 |
Waste-to-energy |
| 50 |
Sugar |
| 474 |
Biomass |
| 257 |
Power generation targets:
| 2014/2015 levels (GWh) | 2019/2020 targets (GWh) |
Power generation targets (fossil and non-fossil) | 9,515.27 | 63,207 |
Electrification targets:
| 2014/2015 levels (% of population) | 2019/2020 (% of population) |
Electrification targets | 60% | 90% |