Kyrgyzstan’s high dependence on hydropower exposes it to the risk of electricity shortages during periods of water scarcity. These risks are magnified by the growing fragility of the power system, which is in urgent need of generation and network investment to improve its operational reliability and to ensure that it has sufficient capacity to meet demand over time. The challenge is further amplified by rapidly growing electricity demand, fuelled by unsustainably low regulated electricity prices, which threatens to quickly outstrip domestic production capacity. Maintaining access to reliable electricity services is likely to become increasingly problematic in these circumstances, especially during periods of water shortage. 


Key challenges for strengthening power system security

Kyrgyzstan’s power sector is relatively small with total generating capacity of around 3.9 gigawatts, producing around 15.4 terawatt-hours (TWh) in 2020. Hydroelectric plants dominate the sector, representing 78% of total generating capacity. The remaining generating capacity is largely provided by thermal CHP plants serving the main population centres. The sector’s heavy dependence on hydroelectric plants is reflected in domestic power production levels, with hydropower typically representing around 90% of Kyrgyzstan’s annual power output during normal hydrological periods. The figure below shows current generating capacity and recent trends in power production in Kyrgyzstan.

High dependence on hydropower raises concerns about maintaining the reliability of electricity supply and power system resilience during periods of water shortage. For instance, the power production trends presented in the figure below reflect the impact of water shortages on hydropower production during the last major water scarcity event in 2015 and 2016. During this period, average hydropower production fell to around 11 300 gigawatt-hours (GWh) per year, representing a fall of nearly 1 800 GWh (13.6%) compared with the ten-year average, with most of the production loss experienced during the winter months of 2015 and 2016.1

As a result, Kyrgyzstan experienced significant power shortfalls and rolling blackouts during the winter peak heating seasons in 2015 and 2016. Power shortages also led to substantial increases in relatively expensive power imports and increasing power production from Bishkek’s CHP plant during the winter period for the duration of this event, placing additional financial pressure on an already cash-strapped sector.2

Electricity production in Kyrgyzstan, 2010-2020

Open

Power generating capacity in Kyrgyzstan, 2020

Open

Reliability and resilience risks are magnified by the age and relative fragility of Kyrgyzstan’s electricity infrastructure, as shown in the figure below. The vast majority of the hydroelectric fleet is well over 30 years old, with a weighted average age of over 40 years and nearly 80% of its capital depreciated. Network infrastructure is also relatively old, with over one-third of all transmission lines depreciated and nearly 70% of the substations depreciated. Distribution assets are in similar condition, with depreciation of distribution lines and substations averaging around 60% and 80% respectively.3

Proportion of assets depreciated in Kyrgyzstan, 2020

Open

Distribution of generator capacity by age in Kyrgyzstan, 2020

Open

High levels of depreciation are typically reflected in higher operating costs, higher rates of unplanned outages and higher network losses. The government reported that over 4 600 supply disruptions were recorded in the distribution system in 2019.4 The World Bank also notes evidence of unplanned infrastructure outages resulting from operating old and under‑maintained assets, which served to exacerbate power system security challenges arising from water shortages experienced during the 2015 and 2016 winter peak seasons.5 And the International Monetary Fund recently observed that old and unreliable power infrastructure had added considerable cost for private-sector power consumers in Kyrgyzstan, with economic losses representing around 4% of annual sales.6

Although the government reports significant reductions in distribution network losses over the last five years, they still remain relatively high by international standards with annual average losses of 12.3% recorded across the four distribution companies in 2019.7 This figure is likely to significantly mask seasonal variability. For instance, on average over 75% of the losses in 2020 were recorded during the winter months,8 with average distribution network losses around 14.4% over this period. Winter network losses across the four distribution businesses ranged from 12.8% to 17.0% in 2020.9 These differences are likely to be largely explained by increasing rates of economic loss associated with the winter peak heating season rather than technical losses. However, this seasonal variability suggests that losses may be more significant from an electricity security perspective during winter periods when they are more likely to coincide with water shortages that jeopardise hydropower production.

The combination of hydro dependence and ageing electricity infrastructure greatly increases Kyrgyzstan’s exposure to potential power supply shortages and power system failures, especially when the power system is under additional stress during periods of water scarcity.

These risks are compounded by rapidly increasing demand for electricity, especially in the residential sector, which is a key driver of growing power demand during the peak winter season. The figure below shows that in 2020, the residential sector dominated power use, accounting for 76% of total final electricity consumption. The industrial sector was the next-largest electricity consumer in 2019, accounting for around 12% of total final electricity consumption. In 2020, around two-thirds of annual electricity consumption occurred during the winter period for all consumer classes except the agricultural sector, reflecting growing use of electricity for space heating, especially among residential consumers.10

Electricity consumption trends in Kyrgyzstan, 2010-2020

Open

Share of electricity consumption in Kyrgyzstan, 2020

Open

Total final consumption of electricity grew by 72% between 2010 and 2020, to around 12 260 GWh. The figure below confirms that rapid growth in residential electricity consumption was the primary contributor to growing power consumption over the period. Residential electricity consumption grew by nearly 170% between 2010 and 2020, to 9 320 GWh. By contrast, trends in electricity demand among the other consuming sectors were variable and subdued, exhibiting little or no growth over the period.

These trends have implications for pursuing power sector reliability and resilience. Residential power consumption is the key driver of growing power demand during the peak winter season, which is also the most likely period for water shortages to jeopardise the reliability of hydropower production. This suggests some potential priorities for power system security policies, in particular, for demand-side management programmes seeking to reduce power use during future power shortages.

Rapid growth in residential consumption has been driven by regulated electricity prices which have been set well below the cost of production. The impact of regulated price movements on consumption can be seen in the figure below, which reflects a significant positive correlation between changes in consumption patterns and changes in regulated tariffs over the period.11 This suggests that Kyrgyz electricity demand is responsive to changes in regulated tariffs. Consumption trends also suggest that the ongoing process of increasing electricity tariffs towards cost-reflective levels would help to moderate the rate of growth in electricity consumption while encouraging greater energy efficiency and ongoing energy savings. This suggests that expediting the tariff reform programme could make a significant positive contribution towards improving power sector reliability and resilience in the present and into the future.

However, electricity prices for the majority of consumption are currently set at levels well below the cost of production, as shown in the figure below. In particular, residential tariffs for the “up to 700 kWh” consumption block have remained unchanged since 2015, despite several policy announcements incorporating tariff increases for this consumption block over recent years.12 The International Monetary Fund has concluded that the current subsidy regime is highly inefficient and poorly targeted, with nearly half of the electricity, district heating and hot water subsidies going to the richest 30% of households, while the bottom 30% receive barely 20% of the subsidies.13

Electricity tariffs as a percentage of the cost of service, Kyrgyzstan, 2018 2019

Open

Residential consumption represents approximately 70% of the electricity load, and the majority of that consumption falls within the “up to 700 kWh” pricing block, which is among the most heavily subsided consumption categories.14 Although commercial and industrial consumers and large-volume residential consumers are paying well over a cost-reflective price for their consumption, the total revenue generated through this cross-subsidy is insufficient to offset the total revenue lost through subsidising the “up to 700 kWh” pricing block.15

Accordingly, the power sector is operating in a financially unsustainable manner that is unable to generate sufficient cash flow to fund necessary maintenance and refurbishment, or to finance new investment in a timely and efficient manner. This has been reflected in dangerously low levels of maintenance and investment, and increasing reliance on foreign grants and project funding from international financial institutions to undertake critical refurbishment and sector modernisation over the last two decades. As a result, the nature, scope and pace of electricity sector modernisation have been constrained, further eroding power sector reliability and resilience over time.

Financial unsustainability is also reflected in ballooning sector deficits, as highlighted in the figure below, which shows the results of modelling undertaken by the World Bank.

Electricity sector deficit forecast in Kyrgyzstan, 2020-2025

Open

World Bank analysis indicates that the electricity sector deficit is likely to increase from around KGS 3 billion (Kyrgyzstani soms) in 2020 to more than KGS 12 billion by 2025 (approximately USD 150 million), assuming no change to current tariffs and no new capital expenditure. Given government ownership of the sector and its level of financial distress, it is likely that any additional debt ultimately will be transferred to the budget.

However, public investment in the power sector is already considerable. International Monetary Fund analysis suggests that electricity sector debt had reached almost 20% of GDP and around 32% of overall public debt in 2016. Loan repayments are projected to continue increasing and to exceed 1% of GDP on average between 2019 and 2023.16 Similarly, the latest World Bank analysis suggests that the energy sector’s cumulative debt has reached KGS 103.3 billion, and is likely to remain steady at around 18% of GDP. At the same time, the loan repayment schedule is forecast to quadruple between 2018 and 2025 before plateauing, assuming no additional debt is incurred.17 The government’s potential to further invest in the sector is likely to be limited by financial constraints and competing policy priorities, placing a substantial financial constraint on public funding of power sector debt and modernisation going forward.

Increasing residential tariffs to cost-reflective levels offers the only viable option for permanently addressing the sector’s cash flow crisis. In 2015, electricity consumption represented between 2.3% and 2.6% of total household expenditure, which was one of the lowest levels recorded in the region.18 In principle, this suggests that most residential consumers may have the financial capacity to pay more cost-reflective tariffs, and that the transition towards cost-reflective tariffs could proceed relatively quickly. However, in practice, increasing electricity prices to cost-reflective levels is unlikely to be feasible in the short term, reflecting limited consumer willingness to pay and likely high community resistance.19 Residential tariff reform has become a highly sensitive political issue, which has resulted in slow and limited action over a long period. Government and regulatory reluctance to address this challenge is reflected in the current Medium-Term Tariff Policy, which envisages no change to the residential “up to 700 kWh” pricing block before 2023.20

Increasing power exchanges through the Central Asian Power System (CAPS) offer considerable potential to help alleviate Kyrgyzstan’s growing power system reliability, resilience and imbalance issues in a timely, proven and cost-effective manner. In particular, greater regional integration could expand the reserves available to help improve Kyrgyzstan’s power system reliability and resilience during periods of water shortage, especially those occurring during winter peak periods, while also providing opportunities for regional electricity exchanges to help address its deteriorating supply-demand balance over time. CAPS was originally designed to operate in an integrated manner across the region, with a view to maximising the potential benefits from an economic and electric reliability perspective for all regional participants.21

However, integrated operation of CAPS has greatly decreased since the member jurisdictions gained their independence and began pursuing electricity security objectives based on greater “self-sufficiency” and “self-reliance”, reflecting growing regional uncertainty and mistrust, and a range of disparate policy objectives. This fundamental shift is reflected in changing patterns of electricity trade, as shown in the figure below.

Electricity trade trends in Kyrgyzstan, 2010-2020

Open

Kyrgyz electricity exports declined substantially over the period, falling from an average of around 25% of total final electricity consumption between 2010 and 2012 to an average of less than 4% of total final electricity consumption between 2014 and 2020. Falling exports over the period have substantially reduced cash flows into the power sector, which has exacerbated the financial instability jeopardising efficient and reliable sector operation and development. At the same time, electricity imports remained low, averaging around 2% of total final electricity consumption over the period. These trends reflect increasing reliance on national operation and management of power systems and electricity supply.

Greater reliance on national operation has exposed inherent weaknesses within the Kyrgyz power system that have the potential to magnify power system security and reliability challenges, especially during periods of water scarcity, while also greatly increasing related management costs. Recent efforts to rebuild regional electricity trade have been led by a number of major infrastructure and technical projects being undertaken with the support of international partners.22 However, various political, economic and infrastructure constraints across the region are likely to limit and slow the realisation of these objectives in practice.

The combination of these factors places Kyrgyzstan’s electricity sector in a precarious position. As a result, Kyrgyzstan’s power services are likely to become less and less reliable and resilient over time, jeopardising power system security. At the same time, if power consumption continues to grow at current rates without corresponding sector investment, it is increasingly likely that the national electricity system will no longer be able to meet demand by the end of the decade at the latest, raising fundamental system adequacy concerns which are likely to worsen considerably over the medium to long term.23


Policies and institutions influencing power system security

The government of the Kyrgyz Republic recognises these challenges and has adopted a strategic policy framework reflecting its ongoing commitment to strengthen power system reliability and resilience, consistent with achieving its wider energy security and self-sufficiency objectives.24 This commitment is reflected in the principal strategic policy objectives guiding the development of the electricity sector, which include:

  • Developing generation and network infrastructure in a manner that will ensure energy security and the self-sufficiency of the power sector.
  • Delivering reliable supply of electricity and heat energy for domestic consumers.
  • Improving the efficiency of electricity and heat generation, transmission and distribution through modernisation and the deployment of new technologies.

A range of policies have been implemented to help realise these policy goals. Principal among them have been several initiatives to rehabilitate and modernise generation facilities. These projects have typically sought to increase generating capacity, improve technical and operating efficiency, and strengthen electricity security. The table below identifies some key examples.

Other potential generation investments are also being proposed including several major renewable generation projects and the possibility of nuclear generation in the longer term.25 Investments in new generating capacity will be needed to address looming electricity supply shortages. However, careful planning and integration of new capacity additions will be required to maximise their contribution to electricity supply while avoiding any unintended power system security outcomes that have the potential to worsen overall reliability of supply. In particular, given the relatively small size of the Kyrgyz power system, the age and fragility of power system infrastructure and the system operator’s limited capacity to manage real-time intermittence, care will be needed to avoid unduly large increments of variable renewable generating capacity, which could greatly increase the risk of operational instability resulting in power system failure. Investment will also be needed in network infrastructure and power system management capability to help improve the flexibility and resilience of the power system as the volume of variable renewable generation increases.

Several projects have been undertaken to reinforce and augment transmission network infrastructure, including regional transmission interconnectors. Crucial among these is the 500 kilovolt (kV) Datka-Kemin transmission line, which was commissioned in 2015 and provides the first substantial transmission path located wholly within Kyrgyzstan’s borders connecting the main generation centres in the south with the main consumption centres in the north. Other network projects with the potential to significantly improve power system security include:26

  • Commissioning of an automated metering and data acquisition (AMDA) system linking 190 substations and generation facilities. The AMDA system aims to help reduce scope for economic losses (theft) and improve monitoring of interregional power flows, bringing them up to the CAPS metering standard.
  • Rehabilitation of over 100 selected substations to improve the reliability of the Kyrgyz power system by replacing circuit-breakers and instrument transformers that have reached the end of their economic lives, are technologically obsolete or do not meet regional standards for accuracy.
  • Installation of a communications and SCADA system for the northern transmission network loop linking seven key substations and the control centre via optical fibre cable. The SCADA system will enable the system operator to make more efficient dispatch decisions based on real-time data. It will also reduce technical losses through avoiding overloading and enable faster detection and restoration of faults. The system has the potential to improve the overall efficiency and reliability of the Kyrgyz power system and CAPS.

Major current and recent generation investment projects in Kyrgyzstan

Project

Description

Investment and scheduled completion

Key partners

Toktogul Hydropower Plant (HPP)

The project includes: replacement of electro-mechanical equipment; complete replacement of all 4 hydro turbines; and the reconstruction of water gates and hydro-mechanical equipment. Capacity is expected to increase from 1200 MW to 1440 MW (an increase of 240 MW; nearly 20%).

USD 385 m (approx.), scheduled for completion in 2024.

Asian Development Bank

Eurasian Development Bank

Eurasian Fund for Stabilization and Development

OJSC “Electric Power Plants of Kyrgyzstan”

Kambarata 2 HPP

The project includes: construction of a second hydro unit with installed capacity of 120 MW; and construction of 110 kV and 500 kV connections to the transmission network. Installed capacity will double to 240 MW; however productive capacity could effectively increase to up to 270 MW as a result of releasing previously ‘locked’ capacity.

USD 110 m (approx.), scheduled for completion in 2024.

Eurasian Development Bank

Eurasian Fund for Stabilization and Development

OJSC “Electric Power Plants of Kyrgyzstan”

Uch-Kurgan HPP

The Uch-Kurgan HPP Modernization Project

includes replacement of four power units, which will increase of installed capacity from 180 MW to 216 MW (an increase of 36 MW; 20%).

USD 145 m (approx.), scheduled for completion in 2025.

Eurasian Development Bank

Eurasian Fund for Stabilization and Development

OJSC “Electric Power Plants of Kyrgyzstan”

At-Bashy HPP

Refurbishment of At-Bashy HPP is expected to increase installed capacity from 40 MW to between 42 MW and 44 MW (an increase of 2-4 MW; 5-10%). Power production is estimated at around 160 GWh per year.

USD 22.2 m (approx.), scheduled for completion in 2021.

Swiss government

OJSC “Electric Power Plants of Kyrgyzstan”

Bishkek Combined Heat and Power (CHP) Plant

The project included the construction of 2 new power units and related infrastructure capable of generating up to 300 MW and up to 300 Gcal of heat. Modernization has increased installed capacity from around 660 MW to 812 MW (an increase of 252 MW; delivering an estimated increase in generating capacity of around 20% and an increase in heat capacity of around 30%). It also allowed fuel switching to locally produced coal.

USD 386 m, completed in 2017.

Export-Import Bank of China

OJSC “Electric Power Plants of Kyrgyzstan”

Sources: State Committee for Industry, Energy and Subsoil Use (2020); IEA (2020), Kyrgyzstan Energy Profile; UNECE (2018), The Kyrgyz Republic: Energy Sector Review in 2018; World Bank (2017), Analysis of the Kyrgyz Republic’s Energy Sector; and various international financial institutions and donor agencies.


In addition, several other projects are proceeding to refurbish and modernise key distribution network infrastructure to help improve reliability and decrease technical and commercial losses. These projects include the reconstruction of electrical networks and installation of advanced metering systems in the Jalal‑Abad, Osh and Batken regions in the south of Kyrgyzstan, and in the Tup and Jeti-Oghuz regions in the east of Kyrgyzstan. Other elements of these projects are seeking to introduce corporate governance reforms and process improvements consistent with best practice established by the International Organization for Standardization.27

Beyond these projects, 455 kilometres (km) of new 500 kV transmission line is planned for Kyrgyzstan under CASA‑1000, which has the potential to strengthen regional interconnection and overall power system reliability from 2023.28 Several related projects are proceeding with the support of international partners.29

Policies to improve energy efficiency and promote energy saving also have considerable potential to strengthen power system reliability and resilience by helping to moderate the rapid growth in electricity consumption. The government has estimated potential electricity savings associated with more efficient energy use at between 20% and 25% of total electricity consumption, while potential energy savings associated with more efficient space heating have been estimated at around 15% of heat consumption.30

Kyrgyzstan has enacted a range of laws in relation to energy efficiency and energy conservation. The primary legislation governing energy efficiency is contained in the Law on Energy Conservation, with more detailed provisions in relation to building energy efficiency provided in the Law on Energy Conservation and Energy Efficiency.31 Implementation is governed by the State Programme on Energy Saving and Energy Efficiency Policy Planning for 2015‑2017, which incorporates a series of targets including an annual decrease in energy intensity of 30% per annum and a decrease in electricity consumption of 5% per year between 2015 and 2025. It is envisaged that much of the energy saving will be delivered through incentives targeting the development and use of energy-efficient appliances, technologies and materials for the production, transmission and consumption of electricity and natural gas by 2020.32

Many of the energy efficiency laws and policies enacted to date are comparable with international best practice, especially those relating to buildings. However, few have been fully or effectively implemented, reflecting relatively weak monitoring and enforcement. As a result, considerable scope remains to increase energy efficiency, especially in the residential and industrial sectors. In addition, there appear to be significant gaps in the policy framework including in relation to establishing minimum energy performance standards, energy labelling of appliances, public procurement and energy audits. A recent peer review of Kyrgyzstan’s energy efficiency policies concluded that considerable scope exists to strengthen and expand the coverage of energy efficiency policies, and to improve monitoring and enforcement.33

Policies in relation to electricity pricing have the potential to substantially strengthen power system reliability and resilience in Kyrgyzstan. Ultimately, cost-reflective electricity pricing is needed to deliver the revenue required to repay debt and to fund investment and modernisation. At the same time, cost-reflective pricing is needed to create robust incentives for more timely and efficient investment, operation and consumption decisions in the power sector. Realising this potential would provide a strong foundation for improving electricity security in the present and beyond.

The most recent step in the electricity and heating price reform programme was taken in September 2021, when the government approved the medium-term tariff policies for electricity, heating and hot water for 2021‑2025, with the objective of making electricity, heating and hot water tariffs more cost-reflective while providing affordable energy for the most vulnerable customers.34 However, the critical challenge of lifting residential electricity tariffs towards cost-reflective levels remains unresolved, with regulated tariffs unchanged since 2015.35 As a result, it appears that electricity pricing policy will continue to constrain efficient and timely power sector development, with the potential to increasingly jeopardise power system adequacy, reliability and resilience into the future.

Institutions and stakeholders

In Kyrgyzstan, institutional responsibility for the electricity sector is distributed among several bodies. The key institutions with roles and responsibilities that substantially determine electricity security outcomes from a policy, regulatory, investment, consumption and system operations perspective include:36

  • The Ministry of Energy, which is responsible for formulating strategic energy sector policy. Its functions include: co‑ordinating energy sector planning and development strategies; creating conditions for the development of renewable energy sources; undertaking monitoring and forecasting of electricity supply and demand balances; and the development of policy measures and regulations to achieve energy sector goals, including incentives for energy efficiency and measures for the modernisation and reconstruction of power plants, substations, power lines and other electric power facilities.
  • The Department for the Regulation of the Fuel and Power Complex within the Ministry of Energy, which is responsible for energy sector regulation. Its functions include: developing tariff methodologies and setting tariffs for electricity, heating and natural gas; licensing for energy sector activities; developing and supervising the performance reporting and monitoring framework for energy sector companies; and undertaking dispute resolution and awareness-raising activities.
  • The Technical Safety Service within the Ministry of Energy, which is responsible for supervising and regulating compliance with safety requirements, land legislation requirements, and technical requirements in the energy sector.
  • JSC Kyrgyz Electricity Settlement Center which was established in August 2015 with the objective of streamlining transactions, improving efficiency and increasing overall financial transparency in the electricity sector. It uses a centralised information and analytical system for collecting, monitoring, analysing and validating data on electricity flows and losses; compiling electricity balances; and calculating financial settlements between electricity sector participants.
  • JSC National Energy Holding, which was established in 2016 to support efforts to improve corporate governance and managerial efficiency within the main state-owned generation and network enterprises. It exercises the government’s controlling stake in key enterprises operating in the electricity sector including JSC Electric Power Plants, JSC Chakan HPP; JSC National Electrical Grid of Kyrgyzstan, the four distribution companies and Bishkek’s district heating service provider JSC BishkekTeploset. It provides direction through its participation on the boards of each of these enterprises, through which it is able to influence key strategic activities and decision-making including appointment of executive board members, approval of company strategies, setting business targets and key performance indicators, performance monitoring, and internal auditing.
  • JSC National Electrical Grid of Kyrgyzstan, which is responsible for all aspects of national power system operation including management of generation dispatch and power flows on the main transmission system to ensure reliable, secure and stable delivery of electricity services to all consumers. It also shares responsibility for co‑ordinating the management of power system security with other national system operators within the CAPS region. Accordingly, it has a pivotal role in maintaining electricity reliability and ensuring power system security within Kyrgyzstan.

Recent changes to institutional arrangements, in particular the creation of JSC National Energy Holding, have served to consolidate public management and control of the Kyrgyz power sector. This could be viewed as a retrograde step from the perspective of establishing a more liberalised power sector characterised by greater efficiency, innovation, competition and transparency. Greater consolidation may also increase the challenge facing regulators, particularly in relation to performance monitoring and implementing best practice forms of incentive regulation which could be deployed, among other things, to help strengthen electricity security outcomes. Access to accurate and timely information will be crucial for addressing these issues. JSC Kyrgyz Electricity Settlement Center is likely to have a key role to play in helping to address the information asymmetries facing regulators and policy makers in this context.

References
  1. See IEA (2022) for further details. 

  2. See IEA (2020), IMF (2019) and World Bank (2017) for further discussion. Similar outcomes were experienced during the preceding major water shortage event in 2008‑2009. See World Bank (2014) for further details.

  3. See State Committee for Industry, Energy and Subsoil Use (2020) for details.

  4. The annual number of disruptions recorded has been steadily decreasing over the last six years, with the 2019 result around half of the number of supply disruptions recorded in 2014. See State Committee for Industry, Energy and Subsoil Use (2020) for further details

  5. See World Bank (2017), pp. 25-26 for details.

  6. See IMF (2019), p. 7 for further discussion. 

  7. See State Committee for Industry, Energy and Subsoil Use (2020), which reports average distribution network losses of around 12.3% in 2019, down from around 16.5% in 2014. 

  8. In this context, “winter” months are defined to include the six-month period from October to March inclusive. 

  9. See JSC National Settlement Center (2021) for further details. 

  10. Analysis drawing this conclusion has been presented in several recent publications including: World Bank (2020), pp. 7‑11; IMF (2019), p. 7; ECS (2018); World Bank (2017), pp. 26-28; and World Bank (2014).  

  11. For example, the changes in consumption patterns observed in 2014‑2015 reflect the initial implementation of the Medium-Term Tariff Policy 2014‑2017, which included the introduction of a highly concessional 700 kilowatt-hour (kWh) tariff block for residential customers and significant increases in tariffs for non‑residential and high-volume residential consumers. See Government of the Kyrgyz Republic (2014) for further details.

  12. Regulated tariffs applying to the bulk of load have not increased since 2015, despite several announced policies calling for tariff increases over the period. See Government of the Kyrgyz Republic (2021a), Government of the Kyrgyz Republic (2021b), Government of the Kyrgyz Republic (2020) and Government of the Kyrgyz Republic (2014) for further details. 

  13. See IMF (2019), p. 21 for further discussion.

  14. The World Bank estimates that 81% of residential consumption is subsidised through the “up to 700 kWh” tariff block. See World Bank (2017), p. 39, for further discussion.

  15. See World Bank (2017), p. 34, for further discussion. 

  16. See IMF (2019), p. 21, for details.

  17. See World Bank (2021) for details. 

  18. See World Bank (2017), pp. 37-38, for further discussion.

  19. See World Bank (2017), p. 39, for further discussion.

  20. See Government of the Kyrgyz Republic (2021a) for details. In addition, under a Presidential Decree of 6 December 2021, electricity tariffs for low-income families with children under 16 years receiving the state allowance decreased from 0.77 KGS to 0.50 KGS for consumption below 700 kWh per month, effective from 1 January 2022. 

  21. See World Bank (2010b), pp. 10-25, for a good overview of CAPS, and the original principles governing its operation and development.  

  22. Several international financial institutions and development agencies are actively supporting countries in the region to improve the reliability of their power supply through infrastructure expansion, upgrade and modernisation, and by encouraging stronger regional integration of national power systems. Leading examples include the Central Asia South Asia Electricity Transmission and Trade project (CASA-1000), and the Central Asia Regional Electricity Market project (CAREM).

  23. See IMF (2019), p. 18, for further discussion.

  24. See Government of the Kyrgyz Republic (2008) and Government of the Kyrgyz Republic (2012) for details.

  25. See Government of the Kyrgyz Republic (2022), KyrgyzKabar News Agency (2022a), KyrgyzKabar News Agency (2022b), KyrgyzKabar News Agency (2022c), Kaktus Media (2022a) and Kaktus Media (2022b) for further information about the latest generation project proposals.

  26. See ADB (2021) and ADB (2020) for further details. 

  27. These projects are proceeding with the support of the European Bank for Reconstruction and Development and the European Union. See EBRD (2021a), EBRD (2021b) and UNECE (2018) for details. 

  28. The CASA‑1000 project involves the construction of a 1 200 km high-voltage transmission line to facilitate seasonal trade among Kyrgyzstan, Tajikistan, Afghanistan and Pakistan. The project was approved in 2012 by all participating countries. Construction commenced in 2019. The completion of the Kyrgyz component is planned for 2023. See IEA (2020) for further details. 

  29. For instance, the United States Agency for International Development (USAID) has committed USD 400 000 to provide secretariat support for the CASA‑1000 project and to provide technical assistance, advisory services and capacity building to multiple stakeholders in Kyrgyzstan in the context of promoting the development of CAREM. See USAID (2021a) and USAID (2021b) for further details. 

  30. See Government of the Kyrgyz Republic (2015) for details.

  31. See Government of the Kyrgyz Republic (1998) and Government of the Kyrgyz Republic (2011) for details. 

  32. See Government of the Kyrgyz Republic (2015) for further details regarding the targets and policy measures.

  33. See ECS (2018) for further details regarding Kyrgyzstan’s energy efficiency policies and practices.  

  34. See Government of the Kyrgyz Republic (2021a) and Government of the Kyrgyz Republic (2021b) for further details. 

  35. See World Bank (2021) and IMF (2019) for further discussion of recent tariff reform developments and related issues. 

  36. See IEA (2020), p. 10; UNECE (2018), pp. 18‑20; and World Bank (2017), Appendix A, for further details.