Environmental Impact Assessment
This decree states the requirement for environmental impact analysis for electricity generation projects. It also includes the requirement for a decommissioning plan and a decommissioning guarantee which is determined on a case-by-case basis.
The following renewable energy related projects/activities require environmental impact assessments:
- Water dams that have a capacity of 2 million m3 or surface area of 100 hectare
- All bioenergy projects using residues.
- All renewable energy plants with more capacity than 10 MW
Want to know more about this policy ? Learn more
Technologies